Lake Tekapō Canal Remediation
Client: Genesis Energy
Taylors Contracting was the main earthworks contractor for this project which was subject to extremely tight timeframes and deadlines.
The scope of works included installation and subsequent removal of coffer dams, removal of existing clay to waste, importing material to re-line the canal embankments, excavation of ‘key’ trenches for liner installation, the import and placement of under liner sands, and the trimming of batter slopes.
Stage One of the project was delivered 10 days ahead of schedule and Stage Two was delivered 13 days early.
Click on the image below to view a video about the project made by Genesis Energy: