Lake Tekapō Canal Remediation

SONY DSC

Client: Genesis Energy

Taylors Contracting was the main earthworks contractor for this project which was subject to extremely tight timeframes and deadlines.

The scope of works included installation and subsequent removal of coffer dams, removal of existing clay to waste, importing material to re-line the canal embankments, excavation of ‘key’ trenches for liner installation, the import and placement of under liner sands, and the trimming of batter slopes.

Stage One of the project was delivered 10 days ahead of schedule and Stage Two was delivered 13 days early.

Click on the image below to view a video about the project made by Genesis Energy:

Other Taylors Projects

Harvest Tracking Hira Forest

Forestry Services Snapshot 2023-2024

Screenshot 2024-09-20 at 2.36.29 PM

Labyrinth Weir

Screenshot 2024-09-20 at 2.32.48 PM

Waimea Community Dam 2024

Screenshot 2024-09-20 at 2.27.18 PM

Upper Motueka Flood Recovery

Screenshot 2024-09-20 at 2.15.26 PM

Blairich Irrigation Reservoir

Upper Condors Stopbank project

Stopbanks – repairing and enhancing community infrastructure

Taylors Contracting Co. Ltd